JSC "Wimm-bill-Dann" is one of the largest producers of dairy products in Russia.
In September 2015, using GeoResin technology, works were performed to stabilize the soil of the base of the floor slab, as well as fill voids in non-operational communications.
The work was completed within 5 days without stopping production, and all signs of work were eliminated.
After the work was completed, Ground Engineering LLC provided a guarantee to Wimm-bill-Dann for the quality of the work with prolonged conditions.
Technological excessive subsidence of a building columns
Stopping subsidence and increasing the load-bearing capacity of the pile foundation
In a residential building, a floor slab sank after a pipe burst
Reinforcement of base soils and re-leveling of floor slab
Leakage of the retaining wall of the entrance to the underground garage
Compaction of soils and plugging of leaks in the retaining wall structure
Eroding the foundation of the supporting columns
Strengthening the foundation foundation without disrupting the entire project schedule
Reinforcement of foundation soils and stabilization of the foundation
Reinforcement of foundation soils and stabilization of the foundation
Strengthening the foundation soil and stabilizing the foundation
Strengthening the foundation soil and stabilizing the foundation
Subsidence of the slab and the appearance of a longitudinal crack
Compaction of the soil with filling the gap under the slab