The building was renovated and reconstructed on the existing old foundation. After the construction of the walls and roof, the foundation settled with deformations that were reflected on the floor slabs.
Within 7 working days, work was carried out to strengthen the soil foundation base with the use of GeoResin DEEP Lifting technology and leveling the floor slabs.
The result of this work was to stop the process of foundation subsidence and re-leveling the working surface of the floor slabs in warehouses.