Uretek

Strengthening of the foundations after an unsuccessful grouting

Industrial building
Category
Treatment facilities
Object
Engineering tanks
Focus
Elimination of foundations subsidence
Location
republic of Tatarstan
Time of work
2020 г.
The timing
3 days
TECHNOLOGY
DEEP Lifting & Floor LIFTING

Task from the client

Strengthening of the ground under the tanks of treatment facilities. Aggravating conditions: weak waterlogged soils and an unsuccessful attempt to stabilize by cementation.

Source data

At the treatment facilities built in 2019, belonging to the processing complex, subsidence of slab foundations began. Taking into account the fact that separate foundations were under various tanks as well as the loads differed, the drawdown was from 3 to 15 centimeters. It was concerned about the high risk of damage to communications passing under the floor slab. We were particularly concerned about the pipelines connecting the treatment facilities. Initially, soil stabilization was done by cementation and after a recorded failure, they turned to GeoResin.

Goal

Strengthening of the soil at the base of slab foundations, stopping the movement of slab foundations under the tanks.

Applied technology

The solution to the problem was provided by the GeoResin DEEP Lifting method, which includes leveling and stabilizing the foundation sediment by strengthening and consolidating the soil in the base with increasing its strength characteristics when injecting a polymer composition. Injections were carried out in two stages: the first stage – the implementation of a geobarrier around a separate slab, then - injection of a geopolymer mixture into three levels. This made it possible to efficiently and accurately use the calculated volume of material to perform slabs stabilization. The second stage-compaction and lifting of the foundations with a tolerance of no more than 5 mm.

Result

The work area was constantly monitored using a laser level during the injection, which showed the rise of structures from 2 to 5 mm. After the work was carried out, the foundation ground was re-tested by dynamic penetration test, which allowed us to assess the improvement of mechanical parameters of the soil in the injection zone. Strengthening of the soil at the base of the foundations took 3 working days.

You can request a call back to discuss the engineering solution and its cost with a specialist.
Back to projects
Standard projects and cost
Leave a comment
Comments
Completed projects
293
  • Services
  • GeoResin methods
  • Projects
  • Video
  • About us
  • Contacts
  • Moscow
    +7 495 268 01 47
    St. Petersburg
    +7 812 627 15 05
    Rostov on Don
    +7 863 308 17 98
    Kazan
    +7 843 206 03 64
    Nizhny Novgorod
    +7 831 429 17 68
    Sevastopol
    +7 869 222 31 91
    Novosibirsk
    +7 383 280 42 61
    GeoResin
    Thank you for your comment!
    Close

    Leave your phone number and our consultant will contact you

    How can I call you?
    Your phone:
    Choose a convenient time to call:

    Leave your email and we will send you this article

    Get a free assessment of the construction and installation solution