Feature
Carrying out of works in the shortest possible time in basement inside the building
Source data
As the initial data, the regulations and production plan developed by the 3rd-party design organization in the scope of the project for major repairs of the production building were adopted. However, the proposed method of reinforcement did not suit the customer due to its complexity and uncertainties associated with the implementation of the proposed design solution.
Goals
Repairs had to be carried out at maximum speed due to the impossibility of carrying out planned construction and installation works above the reinforced area. The work had to be carried out in cramped conditions in the basements inside the building, and the work had to be carried out according to the requirements of the design organization.
Applied technology
According to the accepted design decision, it was necessary to strengthen the soil at the base of the foundation of the load-bearing wall. The solution to the problem was the method of ground injection, provided by GeoResin technology (DEEP Lifting).
Based on the conducted dynamic penetration test, the areas of the decompressed base were identified, and calculations were made for injecting the soil to achieve the required modulus of deformation and compressive strength of the ground for the problem area. In total, 13 injection points were implemented with injections at different levels under the sole of the foundation of the problem wall.
Result
The result was confirmed by laser monitoring during injection, and dynamic penetration tests before and after the works, which allowed us to evaluate the improvement of mechanical parameters of the soil in the injection zone up to five times. The effectiveness of strengthening the base was demonstrated by the fact of vertical lifting of subsided structures up to 0.5 mm. The work lasted 3 working days.
Technological excessive subsidence of a building columns
Stopping subsidence and increasing the load-bearing capacity of the pile foundation
In a residential building, a floor slab sank after a pipe burst
Reinforcement of base soils and re-leveling of floor slab
Leakage of the retaining wall of the entrance to the underground garage
Compaction of soils and plugging of leaks in the retaining wall structure
Eroding the foundation of the supporting columns
Strengthening the foundation foundation without disrupting the entire project schedule
Reinforcement of foundation soils and stabilization of the foundation
Reinforcement of foundation soils and stabilization of the foundation
Strengthening the foundation soil and stabilizing the foundation
Strengthening the foundation soil and stabilizing the foundation
Subsidence of the slab and the appearance of a longitudinal crack
Compaction of the soil with filling the gap under the slab